Construction Submittal Register and Action Codes: CSI 01 33 00 Tracking and PO Release Gates
Releasing a purchase order for fabrication before the construction submittal carries an authorizing action code exposes the contractor to nonconforming material rejection, removal at the contractor’s expense, and withheld progress payments under CSI Division 01 procedures. A project submittal register requires extracting every required submission from individual specification sections, separating approval-gated packages from informational records, and tying each returned review stamp to an explicit purchasing hold or release decision.
Under AIA Document A201–2017 §3.12.7, the Contractor shall perform no portion of the Work requiring submittal review until the respective submittal has been approved by the Architect. Under DoD UFGS Section 01 33 00 (August 2026) §1.16, payment for materials incorporated in the work will not be made if required Designer of Record (DOR) or Government approvals have not been obtained, or if conformance-review or information-only submittals contain errors or deviations. Use the CSI 01 33 00 submittal register and PO release checklist below to audit each package before release, and browse the Procurement guides for related contract and material controls.
Scroll horizontally to see all columns.
| Control gate | Governing specification clause | Operational requirement on the register | Consequence of non-compliance |
|---|---|---|---|
| Register extraction & lock | DoD UFGS 01 33 00 §1.9.1; USACE/DOT 01 33 00 §1.9 |
Preserve Government-delivered definition fields (UFGS: Item No., Spec Paragraph, Description, Classification; USACE/DOT lettered columns c–f); maintain approved schedule fields (UFGS: Activity No., Submit Date, Approval Needed By, Material Needed By; USACE/DOT columns a, g, h, i) |
Omitted specification items remain the Contractor’s obligation even if left off the register or marked N/A (USACE/DOT 01 33 00 §1.10.b) |
| Schedule submission deadline | AIA A201–2017 §3.10.2; Butler Tech 01 33 00 §1.4.A; UFGS 01 33 00 §1.9; UH 01 33 00 §1.4.A.2 |
Submit promptly after award (A201), within 15 days after NTP (Butler Tech), within 20 days after Notice of Award or 30 calendar days after NTP (UFGS), or concurrently with the startup schedule covering the first 60 days (UH) |
No increase in Contract Sum or extension of Contract Time for review time (AIA A201 §3.10.2) or late submittals/resubmittals (VA 01 33 23 §1.4.C) |
| Action vs. Informational split | UH 01 33 00 §1.3.A–B & §1.5.B.3; UFGS 01 33 00 §1.8 & §1.9.6.2; Reclamation 01 33 00 §1.03.C |
Submit Action submittals (Action, G/GA/S, Type A) and Informational submittals (Informational, FIO, Type I) under separate transmittals |
Multi-item transmittals receive one overall action notation (UFGS §1.12.b), and any required change forces resubmission of all items on the transmittal sheet (UFGS §1.13) |
| Contractor QC pre-stamp | AIA A201–2017 §3.12.5–6; VA 01 33 23 §1.5.G–H & §1.10.F.4; UFGS 01 33 00 §1.11.3.e; MHFD 01 33 00 §1.03.C |
Stamp, sign, and date transmittal before submission; use original ink (UFGS §1.11.3.e) and non-red ink for Contractor comments (MHFD §1.03.C) |
Package returned Not Reviewed (NR) / unreviewed for lack of Contractor review evidence or incompleteness (UFGS §1.12.1.d; VA §1.10.F.4; UH §3.2.D) |
Conditional release (MCN / AN) |
UFGS 01 33 00 §1.12.1.b & §1.13; MHFD 01 33 00 §1.02.F.5.c & §1.02.F.8.b; VA 01 33 23 §1.8 & §1.10.F.2; AIA A201 §3.12.8 |
Close 3 written confirmations: (1) no exception / no price or time change, (2) written deviation approval & field dimension check, (3) shop production & corrected O&M copy (30 calendar days post-delivery) |
Unflagged deviations removed at Contractor’s expense (UFGS §1.13; VA §1.5.F); missing O&M data past 30 calendar days authorizes the Contracting Officer to withhold 50 percent of the item price (VA §1.8.B; UFGS §1.5.1 Navy forwarding only) |
Resubmission hold (R&R / RR) |
AIA A201–2017 §3.11, §3.12.7 & §3.12.9; UFGS 01 33 00 §1.11.3.g, §1.12.1.c & §1.16; MHFD 01 33 00 §1.02.F.8.c–d |
Hold fabrication; restrict site record set to approved submittals only; increment revision suffix (061000.01.A, 25B, 18A); flag any non-requested revisions in writing |
Work performed before approval is at Contractor’s own risk (MHFD §1.02.F.9); unflagged resubmission changes are not approved (AIA A201 §3.12.9) |
This guide covers the upstream CSI 01 33 00 and 01 33 23 submittal register and action code rules that feed Stage 3 (Submittal and PO) of the construction material procurement process. Once a package receives its returned action code, record that status and date in the Submittal status column of the material procurement log template separately from the Release authority / decision column. For technical review of fabrication tolerances, weld and hanger details, and Verify in Field (VIF) measurements on the drawings themselves, use the shop drawings review and tolerances guide.
Building the submittal register from Part 1 specifications and version numbering
Extract every submittal line item directly from Part 1 — General (Submittals) of each CSI MasterFormat technical specification section, while applying the register format, numbering syntax, and submission deadlines in Division 01 (01 33 00 Submittal Procedures or VA 01 33 23). Under VA Section 01 33 23 (11-01-23) §1.1.B, required submittals are listed in the SUBMITTALS article of individual specification sections, whereas Division 01 establishes the transmittal, register, and review rules.
Within a single technical specification section, Part 1 — Submittals separates items requiring formal design or government approval from items submitted for information, test verification, or sustainability records. Under DoD UFGS Section 05 12 00 (Structural Steel) §1.2 and DoD UFGS Section 08 11 13 (Hollow Metal Doors and Frames) §1.2, government approval is required for submittals carrying a "G" or "S" classification, whereas submittals without a "G" or "S" classification are for Contractor Quality Control approval and are submitted for information only:
Scroll horizontally to see all columns.
| Specification section | Submittal group (Part 1 — Submittals) | Items requiring approval (G / Action) |
Items for Information Only (no G) or Sustainability (S) |
|---|---|---|---|
DoD UFGS 05 12 00 (Structural Steel, §1.2) |
SD-01 Preconstruction, SD-02 Shop Drawings, SD-05 Design Data |
Erection and Erection Bracing Drawings; G; Fabrication Drawings Including Details of Connections; G; bracketed Design Calculations for Steel Connections; G and Shoring and Temporary Bracing; G |
None in SD-01, SD-02, or SD-05 |
DoD UFGS 05 12 00 (Structural Steel, §1.2) |
SD-03 Product Data, SD-06 Test Reports, SD-07 Certificates |
Sustainability (S): Recycled Content for Structural Steel; S, Recycled Content for Structural Steel Tubing; S, Recycled Content for Steel Pipe; S |
No G (FIO / Contractor QC): SD-03 (Shop Primer; Welding Electrodes and Rods; Direct Tension Indicator Washers; Non-Shrink Grout; Tension Control Bolts); SD-06 (Class B Coating, Bolts, Nuts, and Washers, Weld Inspection Reports, Direct Tension Indicator Washer Inspection Reports, Bolt Testing Reports, bracketed Embrittlement Test Reports); SD-07 (Steel, Bolts, Nuts, and Washers, Welding Procedures and Qualifications, bracketed Galvanizing, Pins and Rollers, AISC certifications) |
U.S. VA 05 12 00 (Structural Steel Framing, §1.4) |
Submittal Drawings, Sustainable Construction, Test Reports, Certificates, Qualifications, Delegated Design |
VA §1.4 lists these without G/FIO labels: Submittal Drawings (size, configuration, fabrication and installation details); Delegated Design Drawings and Calculations (Connection calculations signed and sealed by responsible Architect/Engineer); Recycled Content (post-consumer and pre-consumer percentage by weight); Test Reports (Welders’ qualifying tests); Certificates (Structural steel; Steel connections; Welding materials; Shop coat primer paint); Qualifications (Fabricator; Installer; Welders and welding procedures) |
Not classified as G/Action vs Information Only under VA §1.4 |
DoD UFGS 08 11 13 (Hollow Metal Doors and Frames, §1.2) |
SD-02 Shop Drawings, SD-03 Product Data, SD-04 Samples |
SD-02 (Doors; G; Frames; G); SD-03 (Doors; G; Frames; G); bracketed SD-04 (Factory-applied Enamel Finish; G); Sustainability (S): Recycled Content for Steel Door Product; S, Recycled Content for Steel Frame Product; S |
No G (FIO / Contractor QC): Accessories under SD-02 Shop Drawings and Accessories under SD-03 Product Data |
U.S. VA 08 11 13 (Hollow Metal Doors and Frames, §1.4) |
Submittal Drawings, Manufacturer's Literature, Sustainable, Test Reports, Qualifications, Blast Design Calculations |
VA §1.4 lists these without G/FIO labels: Submittal Drawings; Manufacturer's Literature and Data (door/frame schedule with fire label and smoke control label); Blast Design Calculations (prepared by a qualified blast consultant with a minimum of 5 years of experience in design of blast resistant window systems against threats W1, W2 and GP1, GP2, submitted for review and approval); Recycled Content; Test reports (Sound rated door); Qualifications (Manufacturer) |
Not classified as G/Action vs Information Only under VA §1.4 |
Submittal numbering and revision-suffix conventions
Primary Division 01 specifications do not impose a single universal numbering syntax across all public and private owners. Instead, project manuals prescribe one of three structured identification systems so every initial package and resubmittal carries a unique register ID and file name:
Scroll horizontally to see all columns.
| Numbering convention | Governing specification & clause | Initial submittal format | Resubmittal format | Space reserved on sheet for review stamps |
|---|---|---|---|---|
| CSI Section + Decimal Sequence + Alphabetic Suffix | University of Houston 01 33 00 (01/29/2014) §1.5.D.2, §1.5.D.3.i.1 & §1.5.E.2.a; Butler Tech 01 33 00 §1.2.A (Project Manual section number + sequential number + alphabetic resubmittal suffix) |
UH paper: 061000.01 (Spec Section + decimal + sequential number); UH electronic file: LNHS-061000.01 (with project identifier); Butler: Project Manual section number + sequential number |
UH paper: 061000.01.A; UH electronic file: LNHS-061000.01.A (original number + alphabetic suffix); Butler: original number + alphabetic suffix |
Approximately 6 by 8 inches (150 by 200 mm) on label or beside title block (UH 01 33 00 §1.5.D.2) |
Required Submittal Number (RSN) Section-Sequence Format |
Bureau of Reclamation 01 33 00 (Solicitation 140R4020R0015) §1.03.B, §1.04.C.2 & Table 01 33 00A |
CSI Section + dash + item number: 01 14 10-1, 01 32 10-1, 01 32 10-2, 01 32 10-3 |
Unique transmittal number assigned per submission (§1.04.B.4) | 3 inch by 3 inch space next to title block on D size (22 by 34 in per ASME Y14.1) or half-size (11 by 17 in) sheets |
| Sequential Package Number + Alphabetic Suffix | Mile High Flood District (MHFD) 01 33 00 (Revised 08/2015) §1.02.B.4.b; U.S. VA 01 33 23 (11-01-23) §1.5.E.6 |
Consecutive submittal number (25 in MHFD; 18 in VA) |
MHFD format "XXX-Y" where Y is A, B, C (25B = second resubmittal of Submittal 25); VA consecutive number + letter (18A = resubmission of submittal 18) |
Contractor transmittal stamp and Engineer review stamp per VA 01 33 23 §1.5.G–H |
Locked vs. editable columns on federal and commercial registers
On projects governed by DoD UFGS Section 01 33 00 §1.9, the baseline Submittal Register is exported from SpecsIntact at the conclusion of design; under VA Section 01 33 23 §1.3.C–E, the VA provides a blank Submittal Register (ENGFORM4288-R.pdf) for the Contractor to fill and maintain; USACE/DOT Section 01 33 00 §1.9 governs the Government-delivered register without SpecsIntact export or ENG Form 4288-R. Under USACE/DOT 01 33 00 §1.9, the Contractor must not alter the Government-delivered definition columns (c, d, e, and f) and must retain the approved schedule baseline in columns (a, g, h, and i), while updating the operational tracking columns as submittals progress; under UFGS 01 33 00 §1.9.1, the same fields are locked by name (Item No., Specification Paragraph Number, Description of Item Submitted, and Classification) without letter codes:
- Locked Government-delivered definition columns (
cthroughf): Column(c)Item No., Column(d)Specification Paragraph Number, Column(e)Description of Item Submitted (SDnumber and type, such asSD-02 Shop Drawings; one principal paragraph facilitating location, which underUFGS §1.9.1does not limit project requirements), and Column(f)Classification (G/GAfor Government Approval,BLANK/FIOfor Information Only,S/S/FIOfor Sustainable requirements, plus Design-Build codesDAfor Designer of Record Approval,CRfor Government Conformance Review,DA/CR, andDA/GAunderUFGS §1.9.6.2–1.9.6.3). - Approved baseline schedule columns (
a,g,h, andi): Column(a)Activity Number from the project schedule, Column(g)Contractor Submit Date (scheduled date for the approving authority to receive the submittal), Column(h)Contractor Approval Needed By Date, and Column(i)Contractor Material Needed By Date (date the Contractor needs material delivered to Contractor control underUFGS §1.9.3). - Active transmittal and review log columns (
bandjthroughq): Column(b)Contractor-assigned consecutive Transmittal Number, Column(j)Contractor Action Code, Column(k)date of Contractor QC review action, Column(l)date of submittal transmission/receipt, Columns(m)through(p)review action dates and approving authority action code (o), and Column(q)date approval is received / returned to the Contractor (USACE/DOT 01 33 00 §1.9.2–1.9.4).
On commercial and institutional projects using University of Houston Section 01 33 00 §1.4.A.4, the Contractor’s tabular Submittal Schedule must arrange seven required fields in chronological order: (a) scheduled date for first submittal, (b) Specification Section number and title, (c) submittal category (Action; informational), (d) name of subcontractor, (e) description of the Work covered, (f) scheduled date for the Architect’s final release or approval, and (g) scheduled date of fabrication. Under UFGS 01 33 00 §1.9.7 and VA 01 33 23 §1.3.E, the Contractor must submit formal monthly electronic updates to the register—and under UFGS §1.9.7 and USACE/DOT §1.9.5, deliver an updated copy with each progress payment invoice request.
Takeaway: Build the register directly from every technical section’s Part 1 — Submittals list, lock the specification paragraph and classification columns, and enforce one revision-suffix syntax across both the log and PDF filenames.
Action submittals vs. informational submittals: why mixing them stalls design review
Separate Action Submittals from Informational Submittals on the register and transmit them in separate packages. Combining approval-gated drawings with informational certificates in a single transmittal violates Division 01 packaging rules, subjects the entire transmittal to a single overall review stamp, and clogs the Architect/Engineer’s design review queue.
Under University of Houston Section 01 33 00 §1.3.A–B & §3.2.A–B, AIA Document A201–2017 §3.12.4, DoD UFGS Section 01 33 00 §1.8, and Bureau of Reclamation Section 01 33 00 §1.03.C, the two categories follow distinct contractual tracks:
- Action Submittals (
Action, UFGSG/GA/DA, Reclamation TypeA): Written and graphic information and physical samples (Shop Drawings,Product Data,Samples, and delegatedDesign Data) that require the Architect’s, Designer of Record’s, or Contracting Officer’s responsive approval action before fabrication or work proceeds (UH §1.3.A; Reclamation §1.03.C.1). The reviewer marks required corrections, applies an action stamp, and returns the package (UH §3.2.A). - Informational Submittals (
Informational, UFGS no-G/FIO, Reclamation TypeI): Written and graphic information (Test Reports,Certificates,Qualifications, welding procedures, and schedule updates) that do not require the Architect’s or Contracting Officer’s responsive approval action (UH §1.3.B; AIA A201 §3.12.4; UFGS §1.8; Reclamation §1.03.C.2). Under UH Section 01 33 00 §3.2.B, informational submittals are reviewed and not returned, or returned if they do not comply with requirements; under UFGS Section 01 33 00 §1.8, informational submittals are normally not returned (or marked"receipt acknowledged"/RA), though the Government reserves the right to return unsatisfactory informational submittals for resubmission.
Failing to segregate Action and Informational submittals creates three documented bottlenecks during review:
- Direct breach of separate-transmittal mandates: University of Houston Section 01 33 00 §1.5.B.3 explicitly requires: “Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.” Furthermore, under VA Section 01 33 23 §1.5.D, all irrelevant or unnecessary data must be removed, and submittals containing an excessive amount of irrelevant or unnecessary data will be returned without review. Under AIA A201–2017 §3.12.4 and UH Section 01 33 00 §3.2.E, submittals not required by the Contract Documents may be returned by the Architect without action.
- Whole-transmittal hold from a single deficient item: Under DoD UFGS Section 01 33 00 §1.12.b, when a transmittal sheet includes multiple line items, the reviewer marks the submittal with the overall action notation, not individual line items (noting
"Item 00 - No Comments"only in the comment sheet for clean items). Under UFGS §1.13, if changes are necessary to submittals, the Contractor must revise and resubmit all submittal items on the transmittal sheet. Bundling ten informational mill certificates or product data sheets on the same transmittal as a shop drawing means a single comment on one item holds the entire transmittal under a revise-and-resubmit notation. Conversely, where related action submittals require cross-coordination, UH Section 01 33 00 §1.5.B.4.a permits the Architect to withhold action until related submittals are received, and USACE/DOT Section 01 33 00 §1.10 requires concurrent submission of interrelated component items forming a system. - Misaligned review clocks and preparatory gates: Action submittals require dedicated A/E or Contracting Officer review periods ranging from
7 daysto30 working days, whereas UFGS Information Only (FIO) submittals are certified by the Contractor’s QC Manager and submitted a minimum of14 calendar daysprior to the Preparatory Meeting for the associated Definable Feature of Work (DFOW) under UFGS Section 01 33 00 §1.8.
Because review turnaround periods are set by individual Division 01 specifications rather than a single industry-wide day count, enter the contract’s exact review clock and calendar basis into the register:
Scroll horizontally to see all columns.
| Contract / specification standard | Initial submittal schedule deadline | Contract review turnaround period | Special review-clock extensions or rules |
|---|---|---|---|
| AIA Document A201–2017 (§3.10.2, §3.12.5, §4.2.7) | Promptly after being awarded the Contract | In accordance with the approved submittal schedule, or with "reasonable promptness" |
No fixed day count in A201; Contractor gets no time extension or sum increase if failing to submit or follow an approved submittal schedule (§3.10.2) |
Butler Tech 01 33 00 (§1.2.H, §1.4.A) |
Within 15 days after Notice to Proceed |
7 days for Architect’s review |
Excludes delivery time to and from the Contractor (§1.2.H) |
Mile High Flood District 01 33 00 (§1.02.B.2, §1.02.F.10) |
Per project schedule requirements | 14 calendar days after receipt by Engineer |
Unless specified otherwise, 6 paper copies submitted (4 retained by Engineer, 2 returned); faxed submittals not accepted (§1.02.B.2) |
University of Houston 01 33 00 (§1.4.A.2, §1.5.C.1, §1.5.C.3) |
Concurrently with startup schedule (covering first 60 days + long-lead items) |
15 days for initial review; 15 days for each resubmittal |
Allow additional time if coordination with subsequent submittals is required (§1.5.C.1) |
U.S. VA 01 33 23 (§1.3.E, §1.6.D, §1.10.D–E) |
Prior to acquisition; formal monthly electronic updates | 15 business days for submittals (10 business days for RFIs) |
Electronic submittals smaller than 5 MB may be emailed (§1.6.D); no delay costs or time extensions allowed for late submittals or resubmittals (§1.4.C) |
DoD UFGS 01 33 00 (Aug 2026, §1.8, §1.9, §1.10.4, §1.11) & USACE/DOT 01 33 00 (§1.10) |
Usually within 20 days after Notice of Award (30 calendar days after NTP on Army Design-Build) |
30 calendar days (or Navy tailoring: 15 working days for QC Manager, 20 working days for Contracting Officer, 30 working days for Government fire protection engineer) |
+14 working days when proposing variations (UFGS §1.10.4); +7 calendar days on register for refrigeration and HVAC control systems (USACE/DOT §1.10); FIO submittals due 14 calendar days before DFOW Preparatory Meeting (UFGS §1.8) |
Takeaway: Keep Action Submittals (G/GA/A/S) and Informational Submittals (FIO/I) on separate transmittals so compliance paperwork never holds up fabrication-critical shop drawings.
Submittal action stamp codes and the 3 confirmations before MCN PO release
Treat the returned review stamp as a contractual gate on purchase order release, not a filing formality. While commercial architectural practices and federal agencies use different stamp legends and single-letter codes, every returned notation maps to one of five operational dispositions.
The table below cross-walks the review stamp wordings and register codes documented across DoD UFGS Section 01 33 00 §1.9.6.1 & §1.12.1, U.S. VA Section 01 33 23 §1.10.F, Mile High Flood District (MHFD) Section 01 33 00 §1.02.F.8, USACE/DOT Section 01 33 00 §1.9.4, and commercial submittal workflows (Submittal.app and Layer App):
Scroll horizontally to see all columns.
| Operational gate | Commercial / municipal stamp wording | Federal UFGS / VA / USACE codes & wording | Can fabrication / PO release proceed? | Required contractor action |
|---|---|---|---|---|
| 1. Unconditional Release | No Exceptions Taken (NET) / Approved (Submittal.app wording; Layer App Codes A, 1; MHFD §1.02.F.8.a) |
UFGS Code A ("Approved as submitted" / "approved" or "accepted", §1.9.6.1 & §1.12.1.a); VA "Approved" (§1.10.F.1) |
Yes | Proceed with fabrication, ordering, and work covered as submitted; file in approved site record set |
| 2. Conditional Release | Make Corrections Noted (MCN) / Furnish as Noted / Approved as Noted (MHFD §1.02.F.8.b; Submittal.app wording; Layer App Codes B, 2) |
UFGS Code AN ("Approved as noted" / "approved, except as noted, resubmittal not required", §1.9.6.1 & §1.12.1.b); VA "Approved as noted" (§1.10.F.2) |
Yes, only after closing 3 written confirmations | Incorporate all marked corrections without resubmission, provided Contractor takes no exception (UFGS §1.12.1.b) and provides corrected O&M copy where applicable (MHFD §1.02.F.8.b) |
| 3. Fabrication Hold & Resubmission | Revise and Resubmit (R&R) (MHFD §1.02.F.8.c; Submittal.app); See Remarks / Layer App Codes C, 3 |
UFGS Code RR ("Disapproved as submitted"; "Resubmit" / "revise and resubmit", §1.9.6.1 & §1.12.1.c); VA "Disapproved, revise and resubmit" (§1.10.F.3) |
No — strict fabrication hold | Do not proceed with work; revise and resubmit with incremented suffix (061000.01.A, 25B, 18A) until returned with an approval mark |
| 4. Complete Rejection | Rejected (REJ) / Not Approved (MHFD §1.02.F.8.d; Submittal.app wording; Layer App Codes D, 4) |
No separate UFGS Rejected code ("not approved" / "disapproved" fall under RR at §1.12.1.c); MHFD "REJECTED" (§1.02.F.8.d) |
No — strict fabrication hold | Proposed material, equipment, or unflagged deviation does not comply; prepare and submit a new compliant package (MHFD §1.02.F.8.d) |
| 5. Administrative Return / Record Only | Returned without review (MHFD §1.02.C.5); For Record Only / For Information Only (FIO) & Void / Cancelled (Layer App) |
UFGS/VA Code NR ("Not Reviewed", UFGS §1.9.6.1 & §1.12.1.d; VA §1.10.F.4); USACE/DOT Code NR ("Not Received", §1.9.4); UFGS Code RA ("Receipt Acknowledged", §1.9.6.1 & §1.12.1.e) |
No (NR holds work; RA/FIO is non-approval record; Void is superseded) |
For NR: apply missing Contractor QC stamp/signature or complete missing items and resubmit; for RA/FIO: log receipt for compliance record |
The 3 mandatory written confirmations before releasing a PO on Make Corrections Noted (MCN)
A stamp of Make Corrections Noted (MCN), Approved as Noted (AN), or Furnish as Noted prevents a full resubmittal cycle on minor items, but it does not grant an unconditional green light to release the purchase order as originally quoted. Before issuing a formal Release for Fabrication to the manufacturer or fabricator under an MCN / AN disposition, the buyer and project engineer must close three written confirmations:
- Written No-Exception & Commercial Impact Confirmation (Price and Schedule Gate):
Under DoD UFGS Section 01 33 00 §1.12.1.b, submittals marked
"approved as noted"or"approved, except as noted, resubmittal not required"authorize proceeding with the work covered only “provided that the Contractor takes no exception to the corrections.” Under UFGS §1.13 and USACE/DOT Section 01 33 00 §1.12, if the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, the Contractor must give written notice to the Contracting Officer as required under the FAR clause titledCHANGES. Likewise, Mile High Flood District (MHFD) Section 01 33 00 §1.02.F.5.c specifies that if the Engineer approves variations from contract requirements, an appropriate Contract Modification may be issued unless the variation is minor and involves no change in price or time of performance. Before releasing the PO, obtain the supplier or fabricator’s written confirmation that all reviewer redlines will be executed with zero exception and zero adjustment to the PO price or confirmed delivery date—or hold fabrication until a Change Order or Contract Modification is executed. - Written Deviation Authorization & Field/Interface Dimensional Verification (Technical Gate): Under AIA Document A201–2017 §4.2.7, the Architect’s review is conducted only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents; it is not conducted for determining the accuracy and completeness of dimensions and quantities, or for substantiating installation instructions or performance of equipment or systems. Under AIA A201–2017 §3.12.6, the Contractor remains responsible for determining and verifying materials, field measurements, and field construction criteria. Furthermore, under AIA A201–2017 §3.12.8, the Architect’s approval of a specific item does not indicate approval of an assembly of which the item is a component, and does not relieve the Contractor of responsibility for deviations from the Contract Documents unless the Contractor specifically notified the Architect in writing at the time of submittal (on a separate sheet on Contractor’s letterhead per UH Section 01 33 00 §1.5.G, or with a side-by-side comparison of the proposed item against the specified item per VA Section 01 33 23 §1.5.F) and received written approval as a minor change or a Change Order / Construction Change Directive. Under UFGS §1.13 and VA §1.5.F, failure to point out deviations allows the Government to require removal and replacement of the work at the Contractor’s expense. Confirm in writing that every redlined dimension aligns with verified field measurements and that any contract deviation carries explicit written authorization.
- Written Shop Production Incorporation & Corrected O&M Record Schedule (Execution and Payment Gate):
Under VA Section 01 33 23 §1.10.F.2 and MHFD Section 01 33 00 §1.02.F.8.b, authority to proceed under
"Approved as noted"or"FURNISH AS NOTED"is conditioned on implementing the work in strict accordance with the noted corrections—and under MHFD §1.02.F.8.b, where submittal information will be incorporated into Operation and Maintenance (O&M) data, a corrected copy shall be provided. Under VA Section 01 33 23 §1.8.A–B and the Navy forwarding provisions of DoD UFGS Section 01 33 00 §1.5.1 documented in our material procurement process guide, O&M data for a given item must be submitted within30 calendar daysafter the item is delivered to the contract site; if the Contractor fails to deliver O&M data within that time limit, the Contracting Officer is authorized to withhold 50 percent of the price of the item from progress payments. Require the supplier to confirm in writing that the redlined sheets are attached to the shop production traveler and schedule the clean, corrected O&M manual package before the 30-day post-delivery clock expires.
Rule of thumb: If a reviewer’s
MCN/Approved as Notedmarkup alters a material grade, dimension, or connection detail in a way that changes supplier cost, lead time, or contract scope, treat the package as on hold and issue a formalChangesnotice rather than releasing the PO.
Takeaway: Never treat Make Corrections Noted as an automatic release; secure written supplier sign-off on price/schedule neutrality, field dimensions, and corrected shop/O&M records before fabrication starts.
Preventing field use of superseded drawings after Revise and Resubmit (R&R)
Quarantine every Revise and Resubmit (R&R), Disapproved, or Rejected package immediately so superseded PDFs never reach shop detailers or field installation crews. Under AIA Document A201–2017 §3.12.7, DoD UFGS Section 01 33 00 §1.12.1.c & §1.13, U.S. VA Section 01 33 23 §1.4.D & §1.10.F.3, and MHFD Section 01 33 00 §1.02.F.8.c–d, no portion of the work covered by a disapproved or R&R submittal may proceed until a revised or new submittal is returned with an approval notation.
Proceeding with fabrication or installation before approval carries severe contractual penalties:
- Contractor bears all rework risk: Under MHFD Section 01 33 00 §1.02.F.8.c–d and §1.02.F.9, the Contractor shall not undertake work covered by a submittal before approval except at its own risk; any work done prior to approval is at the Contractor’s own risk.
- Zero progress payment for unapproved materials: Under DoD UFGS Section 01 33 00 §1.16, no payment for materials incorporated in the work will be made unless all required Designer of Record approvals or required Government approvals have been obtained, nor will payment be made for any conformance-review or information-only submittals found to contain errors or deviations.
- No schedule extension for resubmittal delays: Under AIA Document A201–2017 §3.10.2, the Contractor is not entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals if the Contractor fails to submit a submittal schedule or fails to provide submittals in accordance with the approved submittal schedule. Under U.S. VA Section 01 33 23 §1.4.C, no delay costs or extensions of Contract Time are allowed for time lost in late submittals or resubmittals. Under USACE/DOT Section 01 33 00 §1.10, no delay damages or extensions of Contract Time are allowed for time lost in late submittals.
Enforce four document-control mechanisms whenever a package returns marked Revise and Resubmit (R&R) / RR:
- Approved-Only Site Record Quarantine:
Both AIA Document A201–2017 §3.11 and DoD UFGS Section 01 33 00 §1.11.3.g stipulate that the project site record set must contain approved Shop Drawings, Product Data, Samples, and similar required submittals. Under UH Section 01 33 00 §1.5.I, distribution of submittals to manufacturers, subcontractors, suppliers, fabricators, and installers is limited to final submittals. Never upload an unapproved or
R&RPDF into the active field construction folder or place it on the jobsite plan rack. - Revision Suffix Increment and
VoidLog Separation: When preparing the resubmission, increment the package’s alphabetic revision suffix (061000.01.Aand electronic filenameLNHS-061000.01.Aunder UH Section 01 33 00 §1.5.D.3.i.1 & §1.5.E.2.a;25Bfor the second resubmittal of Submittal25under MHFD Section 01 33 00 §1.02.B.4.b;18Afor the resubmission of submittal18under VA Section 01 33 23 §1.5.E.6). Mark the superseded submission entry asVoid/Cancelled(withdrawn or replaced by another submission, as documented in Layer App), and on the material procurement log template, keep theSubmittal statuscolumn (R&Rand return date) strictly separate from theRelease authority / decisioncolumn (Pending) and theSpecification / drawing referencecurrent revision column. - Whole-Transmittal Resubmission Integrity: Under DoD UFGS Section 01 33 00 §1.13, when changes are necessary to submittals, the Contractor must make the revisions and resubmit all submittal items on the transmittal sheet. Replacing a single loose drawing sheet while leaving earlier sheets circulating on a multi-item transmittal creates mixed-revision packages in the shop; re-issue the complete transmittal package under the new revision suffix.
- Explicit Written Notice of All New and Unrequested Revisions: Under University of Houston Section 01 33 00 §1.5.H.1–2, the Contractor must note the date and content of the previous submittal and clearly indicate the extent of revision in the label or title block. Critically, under AIA Document A201–2017 §3.12.9 and UH Section 01 33 00 §1.5.G, the Contractor must direct specific attention—in writing on an attached separate sheet on Contractor’s letterhead or on the resubmitted submittal itself—to any revisions other than those requested by the Architect on previous submittals. In the absence of such written notice, the Architect’s approval of a resubmission does not apply to those unflagged revisions (AIA A201–2017 §3.12.9).
Takeaway: Keep R&R packages out of the field record folder, increment the alphabetic suffix on every resubmission, resubmit the entire transmittal set, and flag every new revision in writing.
CSI 01 33 00 submittal register and action code PO release checklist
Copy this verification table and gate checklist into your project procurement file to audit each submittal package from initial specification takeoff through purchase order fabrication release.
Scroll horizontally to see all columns.
| Verification stage | Field / document check | Governing standard reference | Status (Pass / Hold) |
|---|---|---|---|
| 1. Register Extraction | Every required item in technical spec Part 1 — Submittals (SD-01 through SD-07, Submittal Drawings, Product Data, Samples, Calculations) entered on register |
VA 01 33 23 §1.1.B; UFGS 05 12 00 §1.2; UFGS 08 11 13 §1.2; VA 08 11 13 §1.4 |
|
| 2. Column Integrity | Government-delivered columns (c–f: Item No., Spec Paragraph, Description, Classification) unaltered; schedule columns (a, g, h, i) aligned with construction schedule |
UFGS 01 33 00 §1.9.1 & §1.9.3 (field names); USACE/DOT 01 33 00 §1.9 (lettered columns) |
|
| 3. Category & Transmittal Split | Action Submittals (Action, G/GA, Type A) packaged on separate transmittals from Informational Submittals (Informational, FIO/S, Type I) |
UH 01 33 00 §1.5.B.3; UFGS 01 33 00 §1.8 & §1.9.6.2; Reclamation 01 33 00 §1.03.C |
|
| 4. Numbering & Stamp Space | Unique ID and revision suffix assigned (061000.01.A, LNHS-061000.01.A, 01 14 10-1, 25B, or 18A); stamp space reserved (6 × 8 in in UH; 3 × 3 in in Reclamation) |
UH 01 33 00 §1.5.D–E; Reclamation 01 33 00 §1.03.B & §1.04.C.2; MHFD 01 33 00 §1.02.B.4.b; VA 01 33 23 §1.5.E.6 |
|
| 5. Contractor Pre-Review Stamp | Contractor QC stamp applied, dated, and signed in original ink (UFGS); Contractor comments in non-red ink (MHFD); deviations listed side-by-side (VA) or on separate letterhead sheet (UH) | AIA A201 §3.12.5–8; UFGS 01 33 00 §1.11.3.e; MHFD 01 33 00 §1.03.C; VA 01 33 23 §1.5.F–H |
|
6. MCN / AN 3-Gate Release |
Written confirmation of: (1) no Contractor/supplier exception & zero price/time change, (2) written deviation approval & field dimension check, (3) shop traveler update & corrected O&M copy (30 days post-delivery) |
UFGS 01 33 00 §1.12.1.b & §1.13; MHFD 01 33 00 §1.02.F.5.c & §1.02.F.8.b; VA 01 33 23 §1.8 & §1.10.F.2; AIA A201 §3.12.8 & §4.2.7 |
|
7. R&R / RR Quarantine |
Fabrication held; superseded PDF excluded from site record set; all items on transmittal sheet revised under new suffix; non-requested revisions flagged in writing | AIA A201 §3.11, §3.12.7 & §3.12.9; UFGS 01 33 00 §1.11.3.g, §1.12.1.c, §1.13 & §1.16; MHFD 01 33 00 §1.02.F.8–9 |
Pre-release verification items
- Confirm that the submittal schedule was submitted within the contract deadline (
15 daysafter NTP in Butler Tech01 33 00,20 daysafter Notice of Award or30 calendar daysafter NTP in DoD UFGS01 33 00, or concurrently with the startup schedule covering the first60 daysin UH01 33 00). - Verify that every variation or deviation has a side-by-side comparison (VA 01 33 23 §1.5.F) or separate Contractor-letterhead notice (UH 01 33 00 §1.5.G) and that an extra
14 working days(UFGS 01 33 00 §1.10.4) or7 calendar daysfor refrigeration and HVAC controls (USACE/DOT 01 33 00 §1.10) is included in the register review window where applicable. - On any
Make Corrections Noted (MCN)/Approved as Noted (AN)/Furnish as Notedreturn, file the supplier’s written confirmation that redlines involve no contract price or time change (UFGS §1.12.1.b & §1.13; MHFD §1.02.F.5.c) and schedule the corrected O&M manual submission within30 calendar daysof site delivery to prevent the50 percentpayment withhold (VA 01 33 23 §1.8.B;UFGS §1.5.1Navy forwarding only). - Record the returned action code and date in the
Submittal statuscolumn of the material procurement log template while keepingRelease authority / decisionseparate until all threeMCNconfirmations are closed.
Frequently asked questions
What is the difference between a submittal schedule and a submittal register?
In commercial contracts such as AIA Document A201–2017 §3.10.2 and University of Houston Section 01 33 00 §1.4.A, the document is called a Submittal Schedule and arranges required submittals chronologically with planned submission, Architect approval, and fabrication dates. In federal specifications, DoD UFGS Section 01 33 00 §1.9 exports the baseline Submittal Register from SpecsIntact, while U.S. VA Section 01 33 23 §1.3 provides a blank ENG Form 4288-R for the Contractor to maintain, and USACE/DOT Section 01 33 00 §1.9 governs the Government-delivered register; once completed with the Contractor’s submit dates, approval needed dates, and material needed dates and approved by the Contracting Officer, on Army Design-Build projects, the approved register under UFGS §1.9.2 serves as the scheduling and control document throughout the contract period; under UFGS §1.9.7 the register is updated monthly and with each invoice request.
Why do architects stamp submittals “No Exceptions Taken” or “Make Corrections Noted” instead of “Approved”?
As documented in AIA Document A201–2017 §3.12.8 & §4.2.7, MHFD Section 01 33 00 §1.02.F.8, Submittal.app, and Layer App, design firms use No Exceptions Taken (NET) and Make Corrections Noted (MCN) / Furnish as Noted to reflect the contractual boundary of design review: checking for general conformance with the information given and the design concept expressed in the Contract Documents. Regardless of whether a stamp reads Approved (UFGS Code A / VA) or No Exceptions Taken, the review does not verify dimensions, quantities, fabrication means, or assembly coordination (AIA A201 §4.2.7), and does not relieve the Contractor of responsibility for errors, omissions, or unflagged deviations (AIA A201 §3.12.8).
Can a contractor release a purchase order for fabrication on an “Approved as Noted” or “Make Corrections Noted” submittal?
Yes, but only conditionally. Under DoD UFGS Section 01 33 00 §1.12.1.b, VA Section 01 33 23 §1.10.F.2, and MHFD Section 01 33 00 §1.02.F.8.b, "Approved as noted" / "FURNISH AS NOTED" authorizes proceeding with fabrication and work without resubmitting only if the Contractor incorporates all noted corrections, takes no exception to the markups, gives formal written notice under the CHANGES clause if any notation constitutes a contract price or time change (UFGS §1.13), and provides a corrected copy where the submittal feeds Operation and Maintenance (O&M) data (MHFD §1.02.F.8.b).
What happens if a submittal package is sent to the architect or contracting officer without the contractor’s QC review stamp?
Under DoD UFGS Section 01 33 00 §1.12.1.d and U.S. VA Section 01 33 23 §1.5.G–H & §1.10.F.4, a submittal that lacks evidence of the Contractor’s review and approval stamp/signature (which under UFGS §1.11.3.e must be signed by the designated QC organization member in original ink rather than a stamped signature) or is incomplete is marked "Not Reviewed" (NR) and returned without review for resubmission. Under VA Section 01 33 23 §1.4.C, no delay costs or time extensions are allowed for time lost in late submittals or resubmittals.
Document references
- DoD Unified Facilities Guide Specifications (UFGS) Section 01 33 00, Submittal Procedures (August 2026): §§1.5.1, 1.8, 1.9, 1.9.1–1.9.7, 1.10.4, 1.11, 1.11.3.e, 1.11.3.g, 1.12, 1.12.1, 1.13, 1.14, and 1.16 (note: opening instructions state not to use this section for Navy Design-Build projects).
- U.S. Department of Veterans Affairs (VA) Master Construction Specification Section 01 33 23, Shop Drawings, Product Data, and Samples (11-01-23): §§1.1.B, 1.3.C–E (ENGFORM4288-R.pdf), 1.4.A–D, 1.5.A–H, 1.6.D, 1.8.A–B, and 1.10.D–F.
- American Institute of Architects (AIA) Document A201–2017, General Conditions of the Contract for Construction: §§3.10.2, 3.11, 3.12.1–3.12.9, and 4.2.7.
- University of Houston Master Construction Specifications Section 01 33 00, Submittal Procedures (01/29/2014): §§1.3.A–B, 1.4.A, 1.5.B–I, and 3.2.A–E.
- Mile High Flood District (MHFD) Standard Specifications Section 01 33 00, Submittal Procedures (Revised 08/2015): §§1.02.B.2, 1.02.B.4.b, 1.02.C.5, 1.02.F.5.c, 1.02.F.8.a–d, 1.02.F.9, 1.02.F.10, and 1.03.C.
- Butler Tech Project Manual Section 01 33 00, Submittal Procedures: §§1.2.A, 1.2.H, and 1.4.A.
- Bureau of Reclamation Solicitation 140R4020R0015 (Big Sandy Dam) Section 01 33 00, Submittals: §§1.03.A–C, 1.04.B–C, and Table
01 33 00A. - USACE QCS / DOT Section 01 33 00, Submittal Procedures: §§1.9, 1.9.1–1.9.5, 1.10, and 1.12.
- DoD UFGS Section 05 12 00, Structural Steel: §1.2 Submittals (
SD-01throughSD-07). - U.S. VA Master Construction Specification Section 05 12 00, Structural Steel Framing (11-01-18): §1.4 Submittals.
- DoD UFGS Section 08 11 13, Hollow Metal Doors and Frames: §1.2 Submittals (
SD-02throughSD-04). - U.S. VA Master Construction Specification Section 08 11 13, Hollow Metal Doors and Frames (01-01-21): §1.4 Submittals (
§1.4.G.1Blast Design Calculations). - Commercial Submittal Stamp References: Submittal.app (Submittal Review Stamps Explained) and Layer App (Submittal Review Status Codes Explained, updated Jun 1, 2026).